(1) In the case of contracts entered into by the Council before the relevant date for the carrying out of works to any transferred property—
(a) if the works are for the construction, rehabilitation or modernisation of, or the carrying out of major works of improvement to, the property; or
(b) if the works arise from a major technical cause,
the Council shall be liable for and entitled to receive any payment due under or in respect of the contract.
(2) The Council shall determine for the purposes of paragraph (1) whether the works arise from a major technical cause and as soon as may be after the relevant date shall notify the appropriate transferee authority of any contract to which that paragraph applies.
(3) The Council may by notice in writing given to a transferee authority require that authority to assign to the Council the benefit and burden of any contract to which paragraph (1) applies, specifying a date when such assignment shall take place and on that date the transferee authority shall so assign the burden and benefit of such said contract notwithstanding any provision in the contract or otherwise purporting to prohibit or restrict such assignment.

---
Source: https://www.legislation.gov.uk/uksi/1980/320/article/6 (the official version)
Page: https://openlegislation.uk/greater-london-council-transfer-of-land-and-housing-accommodation-order-1980/article-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.