# The Greater Manchester (Light Rapid Transit System) (Eccles Extension) Order 1996, Article 32: Extinction or suspension of private rights of way


(1) All private rights of way over land subject to compulsory acquisition under this Order other than in relation to the land numbered 106, 108 and 111 on the land plans and in the book of reference shall be extinguished—
(a) as from the acquisition of the land by the undertaker, whether compulsorily or by agreement, or
(b) on the entry on the land by the undertaker under section 11(1) of the 1965 Act,
whichever is sooner.
(2) All private rights of way over land owned by the undertaker which, being within the limits of land which may be acquired shown on the land plans, is required for the purposes of this Order shall be extinguished on the appropriation of the land for any of those purposes by the undertaker.
(3) All private rights of way over land of which the undertaker takes temporary possession under this Order shall be suspended and unenforceable for as long as the undertaker remains in lawful possession of the land.
(4) Any person who suffers loss by the extinguishment or suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part I of the Land Compensation Act 1961.
(5) This article does not apply in relation to any right of way to which section 271 or 272 of the Town and Country Planning Act 1990 (extinguishment of rights of statutory undertakers, etc.) or paragraph 2 of Schedule 9 (provisions relating to statutory undertakers, etc.) to this Order applies.

---
Source: https://www.legislation.gov.uk/uksi/1996/2714/article/32 (the official version)
Page: https://openlegislation.uk/greater-manchester-light-rapid-transit-system-eccles-extension-order-1996/article-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.