# The Greater Manchester (Light Rapid Transit System) (Mumps Surface Crossing) Order 2001, Schedule 1: SCHEDULED WORKS


In the Borough of Oldham—
Work No. 1 A street tramway 276 metres in length (double line) commencing at a junction with the termination of Work No. 4 of the 1994 Act at a point along Mumps adjacent to its junction with Prince Street, running thence in an easterly direction along Mumps before terminating at a point on the north-western side of the junction of Brook Street and Bottom O' Th' Moor.
Work No. 2 A tramroad 69 metres in length (double line) commencing by a junction with the termination of Work No. 1, running thence in a north-easterly direction along part of the existing Middleton to Shaw railway before terminating at a point adjacent to Wild Street and including the demolition in part of the existing railway viaduct.

---
Source: https://www.legislation.gov.uk/uksi/2001/1368/schedule/1 (the official version)
Page: https://openlegislation.uk/greater-manchester-light-rapid-transit-system-mumps-surface-crossing-order-2001/schedule-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.