After schedule 1, insert—

“Schedule 1A

Information required for registration of an eligible heat pump

Regulation 8A(2)(a)

1

This schedule specifies the information that the Authority may require of an applicant or participant to determine whether a heat pump is an eligible heat pump.

2

The information is (as applicable to the applicant or participant)—

(a)

the heat pump manufacturer and model,

(b)

the commissioning date of the heat pump,

(c)

the system design of the heat pump,

(d)

the energy input and heat output of the heat pump,

(e)

installation certifications for the heat pump,

(f)

markings on schematic diagrams of the heat pump,

(g)

metering information, including any heat loss, provided in a metric as requested by the Authority,

(h)

electrical metering information,

(i)

photographs of the installation of the heat pump,

(j)

documentation expressing the coefficient of performance of a heat pump, with supporting calculations,

(k)

planning permission evidence for the heat pump, and

(l)

any further information which the Authority may require.

3

Information specified in this Schedule must be provided in such a manner and form as the Authority may reasonably request.

4

The costs of providing the information specified in this Schedule are to be borne by the applicant or participant.”.