# The Green Hill Solar Farm Order 2026, Article 14: Access to works


(1) The undertaker may, for the purposes of the authorised development—
(a) form and lay out the permanent means of access, or improve existing means of access, in the locations specified in Part 1 (permanent means of access to works) of Schedule 7 (access to works);
(b) form and lay out the temporary means of access in the location specified in Part 2 (temporary means of access) of Schedule 7; and
(c) with the approval of the relevant planning authority after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.
(2) Unless otherwise agreed with the relevant planning authority, the undertaker must restore any access that has been temporarily created under this Order to the reasonable satisfaction of the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/article/14 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/article-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.