# The Green Hill Solar Farm Order 2026, Part 1: DOCUMENTS AND PLANS


(1)
Document name
(2)
Document reference
(3)
Revision number
(4)
Date
Access to works plan
GH2.7
A
December 2025
Archaeological mitigation strategy
GH6.3.12.6
B
February 2026
Book of reference
GH4.3
F
April 2026
Concept design parameters and principles
GH7.17
D
August 2026
Environmental statement
GH6.1
-
May 2025
Hedgerow and tree protection order plan
GH2.11
B
December 2025
Land plan
GH2.2
E
February 2026
Outline battery storage safety management plan
GH7.7
B
February 2026
Outline construction environmental management plan
GH7.1
D
April 2026
Outline construction traffic management plan
GH7.9
C
March 2026
Outline decommissioning statement
GH7.3
C
March 2026
Outline drainage strategy
GH6.3.10.1
B
February 2026
Outline ecological protection and mitigation strategy
GH7.5
E
April 2026
Outline landscape and ecological management plan
GH7.4
E
March 2026
Outline operational environmental management plan
GH7.2
E
August 2026
Outline operational traffic management plan
GH7.25
A
November 2025
Outline public rights of way and permissive paths management plan
GH7.10
C
March 2026
Outline skills, supply chain and employment plan
GH7.8
-
May 2025
Outline soil management plan
GH7.6
B
August 2026
Public rights of way plan
GH2.6
C
December 2025
Streets plan
GH2.5
C
December 2025
Works plan
GH2.4
G
March 2026
Written scheme of investigation: archaeological trenching
GH8.2.17
-
February 2026

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/13/part/1 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-13/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.