# The Green Hill Solar Farm Order 2026, Paragraph 110


(1) Before beginning to construct any specified work, the undertaker must submit to the drainage authority plans of the specified work, evidence to support said plans and any such further particulars available to it as the drainage authority may within 28 days of the submission of the plans reasonably require (or submission of further particulars if required by the drainage authority).
(2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the drainage authority or determined under paragraph 117.
(3) Any approval of the drainage authority required under this paragraph—
(a) must not be unreasonably withheld or delayed;
(b) is deemed to have been given if it is neither given nor refused within 2 months of the submission of the plans for approval (or the submission of further particulars if applicable) or, in the case of a refusal, if it is not accompanied by a statement of the grounds of refusal; and
(c) may be given subject to such reasonable requirements and conditions as the drainage authority may consider appropriate.
(4) The drainage authority must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3).

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/15/paragraph/110 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-15/paragraph-110
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.