# The Green Hill Solar Farm Order 2026, Paragraph 117


Any dispute between the undertaker and the drainage authority under this Part, unless otherwise agreed, must be determined by arbitration under article 44 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/15/paragraph/117 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-15/paragraph-117
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.