# The Green Hill Solar Farm Order 2026, Paragraph 36: Access


If in consequence of the agreement reached in accordance with paragraph 28 or the powers granted under this Order the access to any apparatus, the SGRE Site and/or the WMEL Site is materially obstructed, the undertaker must provide such alternative means of access to such apparatus, the SGRE Site and/or the WMEL Site as will enable National Grid to access, maintain or use the apparatus, the SGRE Site and/or the WMEL Site no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/15/paragraph/36 (the official version)