# The Green Hill Solar Farm Order 2026, Paragraph 68: Provisional Certificate for cable works


(1) As soon as the undertaker considers that the cable works provisional certificate for the cable works may be properly issued it must apply to National Highways for the cable works provisional certificate.
(2) Following an application for a cable works provisional certificate, National Highways must as soon as reasonably practicable—
(a) inspect the cable works, the strategic road network, and any land in which National Highways has an interest that is affected by the cable works; and
(b) provide the undertaker with a written list of works that are required for the cable works provisional certificate to be issued or confirmation that no further works are required for this purpose.
(3) Within 28 days of the completion of any cable works, the undertaker must submit to National Highways the as built information.
(4) When the cable works, incorporating any further works notified to the undertaker pursuant to sub-paragraph (2)(b), have been completed to the satisfaction of National Highways and the as built information has been provided to National Highways, National Highways must issue the cable works provisional certificate.
(5) The undertaker must make available to National Highways upon request copies of any survey or inspection reports produced pursuant to any inspection or survey of any cable works, following completion of the inspection or survey, that the undertaker may from time to time carry out.

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/15/paragraph/68 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-15/paragraph-68
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.