# The Green Hill Solar Farm Order 2026, Paragraph 13: Construction environmental management plan


(1) No part of the authorised development may commence until a construction environmental management plan for that part has been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
(2) The construction environmental management plan must be substantially in accordance with the outline construction environmental management plan.
(3) Before approving the construction environmental management plan the relevant planning authority must consult with the Environment Agency.
(4) All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan.

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.