Paragraph 14 Operational environmental management plan
(1)
Prior to the date of final commissioning for any part of the authorised development, an operational environmental management plan for that part must be submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
(2)
The operational environmental management plan must be substantially in accordance with the outline operational environmental management plan.
(3)
Before approving the operational environmental management plan the relevant planning authority must consult with the Environment Agency.
(4)
The operational environmental management plan must be implemented as approved.