(1)

Prior to the date of final commissioning of the authorised development, an operational traffic management plan must be submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.

(2)

The operational traffic management plan must be substantially in accordance with the outline operational traffic management plan.

(3)

Before approving the operational traffic management plan the relevant planning authority must consult with the relevant highway authority.

(4)

The operational traffic management plan must be implemented as approved.