# The Green Hill Solar Farm Order 2026, Paragraph 17: Operational noise


(1) No part of Work Nos. 1, 2 or 3 may commence until an operational noise management plan containing details of how the design of that numbered work has incorporated the operational mitigation measures set out in the outline operational environmental management plan for that part has been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple planning authorities, each of the relevant planning authorities.
(2) The operational noise management plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.