  "legislation": "uksi/2026/1074",
  "legislation_title": "The Green Hill Solar Farm Order 2026",
  "legislation_url": "https://openlegislation.uk/green-hill-solar-farm-order-2026",
  "path": "schedule/2/paragraph/19",
  "kind": "paragraph",
  "number": "19",
  "heading": "Soil management",
  "text": "(1) No part of the authorised development may commence until a soil management plan for that part has been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple planning authorities, each of the relevant planning authorities.\n(2) Any soil management plan submitted in accordance with this paragraph must be substantially in accordance with the outline soil management plan as relevant to the activities to which it relates.\n(3) The soil management plan must be implemented as approved.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/1074/schedule/2/paragraph/19",
    "retrieved_at": "2026-10-28T20:54:07.044962+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}