Paragraph 2 Commencement of the authorised development
The authorised development must commence no later than the expiration of five years beginning with the date this Order comes into force.
No part of the authorised development may commence until a written scheme setting out the phase or phases of construction of the authorised development has been submitted to the relevant planning authorities.
The written scheme submitted pursuant to sub-paragraph (2) must include a timetable for the construction of the phase or phases of the authorised development and a plan identifying the phasing areas.
The undertaker must notify the relevant planning authority within fourteen days of the date of final commissioning for a part or parts of the authorised development that the final commissioning of that part or parts has taken place.