# The Green Hill Solar Farm Order 2026, Paragraph 3: Approved details and amendments to them


(1) The undertaker may submit any amendments to any approved document to the relevant planning authority for approval and, following approval, the relevant approved document is to be taken to include the amendments approved under this paragraph.
(2) The relevant planning authority must not approve any amendments under sub-paragraph (1) to any approved document unless it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
(3) In this paragraph, “approved document” means any document certified under article 42 (certification of plans and documents, etc.) and any plans, details or schemes which have been approved pursuant to any requirement.

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-2/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.