Paragraph 6 Battery safety management
(1)
Work No. 2 must not commence until a battery storage safety management plan has been submitted to and approved by the relevant planning authority.
(2)
The battery storage safety management plan must be substantially in accordance with the outline battery storage safety management plan.
(3)
The relevant planning authority must consult with Northamptonshire Fire and Rescue Service and the Environment Agency before determining an application for approval of the battery storage safety management plan.
(4)
The battery storage safety management plan must be implemented as approved.