# The Green Hill Solar Farm Order 2026, Part 1: PERMANENT MEANS OF ACCESS TO WORKS


(1)
Area
(2)
Street
(3)
Description of means of access
District of West Northamptonshire
Broughton Road
The provision of a permanent means of access to the authorised development from the point marked Access-A-1 on sheet 1 of the access to works plan
District of West Northamptonshire
Broughton Road
The provision of a permanent means of access to the authorised development from the point marked Access-A-2 on sheet 1 of the access to works plan
District of West Northamptonshire
Newland Road, Walgrave
The provision of a permanent means of access to the authorised development from the point marked Crossing-A-1 (E) on sheet 1 of the access to works plan
District of West Northamptonshire
Newland Road, Walgrave
The provision of a permanent means of access to the authorised development from the point marked Crossing-A-1 (W) on sheet 1 of the access to works plan
District of West Northamptonshire
Kettering Road
The provision of a permanent means of access to the authorised development from the point marked Access-A.2-1 on sheet 2 of the access to works plan
District of West Northamptonshire
Sywell Road
The provision of a permanent means of access to the authorised development from the point marked Access-B-1 on sheet 6 of the access to works plan
District of West Northamptonshire
Moulton Road
The provision of a permanent means of access to the authorised development from the point marked Access-B-2 on sheet 6 of the access to works plan
District of North Northamptonshire
Sywell Road
The provision of a permanent means of access to the authorised development from the point marked Access-C-1 on sheet 7 of the access to works plan.
District of North Northamptonshire
Highfield Road
The provision of a permanent means of access to the authorised development from the point marked Access-D-2 on sheet 7 of the access to works plan.
District of North Northamptonshire
Highfield Road
The provision of a permanent means of access to the authorised development from the point marked Access-D-4 on sheet 8 of the access to works plan.
District of North Northamptonshire
Highfield Road
The provision of a permanent means of access to the authorised development from the point marked Access-E-1 on sheet 8 of the access to works plan
District of North Northamptonshire
Wilby Road
The provision of a permanent means of access to the authorised development from the point marked Crossing-E-1 (S) on sheet 8 of the access to works plan
District of North Northamptonshire
Wilby Road
The provision of a permanent means of access to the authorised development from the point marked Crossing-E-1(N) on sheet 8 of the access to works plan
District of North Northamptonshire
Mears Ashby Road
The provision of a permanent means of access to the authorised development from the point marked Access-E-2 on sheet 9 of the access to works plan
District of North Northamptonshire
Station Road
The provision of a permanent means of access to the authorised development from the point marked Access-BESS-1 on sheet 13 of the access to works plan
District of West Northamptonshire
Station Road
The provision of a permanent means of access to the authorised development from the point marked Access-BESS-2 on sheet 13 of the access to works plan
District of North Northamptonshire
Station Road
The provision of a permanent means of access to the authorised development from the point marked Access-BESS-3 on sheet 13 of the access to works plan
District of North Northamptonshire
Station Road
The provision of a permanent means of access to the authorised development from the point marked Access-BESS-4 on sheet 13 of the access to works plan
District of North Northamptonshire
Easton Way
The provision of a permanent means of access to the authorised development from the point marked Crossing-F-1 (E) on sheet 14 of the access to works plan
District of North Northamptonshire
Easton Way
The provision of a permanent means of access to the authorised development from the point marked Crossing-F-1 (W) on sheet 14 of the access to works plan
District of North Northamptonshire
London Road (A509)
The provision of a permanent means of access to the authorised development from the point marked Access-F-1 on sheet 15 of the access to works plan
District of North Northamptonshire
Easton Lane
The provision of a permanent means of access to the authorised development from the point marked Access-F-2 on sheet 16 of the access to works plan
District of North Northamptonshire
London Road (A509)
The provision of a permanent means of access to the authorised development from the point marked Access-F-3 on sheet 16 of the access to works plan
Borough of Milton Keynes
Northampton Road (A428)
The provision of a permanent means of access to the authorised development from the point marked Access-G-1 on sheet 18 of the access to works plan

---
Source: https://www.legislation.gov.uk/uksi/2026/1074/schedule/7/part/1 (the official version)
Page: https://openlegislation.uk/green-hill-solar-farm-order-2026/schedule-7/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.