Article 38 Article 4 amended (application for free allocation in 2027-2030 allocation period by operators of incumbent installations)I1
United Kingdom
Article 4 is amended as follows.
In the heading for “2026-2030” substitute “2027-2030”.
In paragraph 1 in the words before point (a) for “2026-2030” substitute “2027-2030”.
For paragraph 1A substitute—
“1a.An application consists of 2 stages to be completed, as follows:
(a)the first stage is that in the period beginning with 1 April 2025 and ending with 30 June 2025, the operator must submit the documents referred to in paragraph 2 to the regulator;
(b)the second stage is that in the period beginning with 1 April 2026 and ending with 30 June 2026, the operator must:
(i)notify the regulator in writing that the operator wishes the application to proceed; and
(ii)where relevant, resubmit the documents referred to in paragraph 2 with any amendments necessary to take account of any changes to free allocation rules for the 2027-2030 allocation period made after 31 March 2025 (for example, changes to the list of sectors and subsectors set out in the Annex to Commission Delegated Decision (EU) 2019/708).
1b.In the case of an operator of an installation included in the hospital and small emitter list for 2026-2030 or the ultra-small emitter list for 2026-2030, a notification under paragraph 1a(b)(i) that the operator wishes the application to proceed must also state whether the operator:
(a)does not wish the installation to be a hospital or small emitter or an ultra-small emitter for the scheme years in the 2027-2030 allocation period (see paragraph 23B of Schedule 7, and paragraph 7A of Schedule 8, to the UK ETS Orderf1); or
(b)wishes the application to proceed for the purpose of Schedule 8A to the UK ETS Order only (free allocation for former hospital or small emitters and ultra-small emitters).”.
In paragraph 2 in the words before point (a) for “An application for free allocation submitted pursuant to paragraph 1 shall be accompanied by the following particulars” substitute “The documents to be submitted are”.
In paragraph 4 omit “allocation” in both places.
After paragraph 4 insert—
“5.Unless both the first and second stages of an application are completed, the application must be treated as never having been made.
6.Despite paragraph 5, Articles 15 and 15a apply in relation to an application as follows:
(a)Articles 15 and 15a(2) and (3) apply after the first stage is completed; and for the purpose of those provisions, an “application” is an application in respect of which the first, but not the second, stage is completed;
(b)Article 15a(4) and (5) apply after both stages are completed; and for the purpose of those provisions, an “application” is an application in respect of which both stages are completed.
7.Where, as part of the second stage under paragraph 1a(b)(ii), the operator resubmits the documents referred to in paragraph 2:
(a)Articles 15 and 15a(2) and (3) apply again in relation to the application, with the following modifications:
(i)any reference to baseline data reports and verification reports must be read as a reference to the resubmitted documents;
(ii)any reference in Article 15a to historical activity levels must be read as a reference to any historical activity levels redetermined under Article 15 as so applied;
(iii)Article 15a(2)(b) applies as if for “30 September 2025” there were substituted “30 September 2026”;
(b)for the purpose of paragraph 6(b), Article 15a(4) and (5) apply in relation to the application taking account of the resubmitted documents.
8.The regulator must notify the UK ETS authority of every notification under paragraph 1a(b)(i) and every case where no such notification is received.”.