Paragraph 12 Article 8 amended (content and submission of the monitoring methodology plan)I1
United Kingdom
Article 8 is amended as follows.
In paragraph 1 for “Articles 4(2)b and 5(2) shall draw up” substitute “ Article 4 or 5 must, except where a monitoring methodology plan has already been approved in relation to the installation under this Article, draw up ”.
In paragraph 3 omit “and for the purposes of Article 12(3) of Regulation (EU) No 601/2012,”.
Omit paragraphs 4 and 5.
After paragraph 3 insert—
“6Where the operator has submitted a monitoring methodology plan to the regulator, the regulator must, by notice to the operator:
(a)if the plan is in accordance with this Regulation, approve it; or
(b)reject it.
7A notice under paragraph 6 must be given:
(a)where the monitoring methodology plan is submitted with an application for free allocation in the 2026-2030 allocation period under Article 4, on or before 31 December 2025;
(b)where the monitoring methodology plan is submitted with an application for free allocation under Article 5, as soon as reasonably practicable after the application is made.”
Annotations
Commencement
- I1
Sch. 1 para. 12 in force at 31.12.2020 on IP completion day, see art. 2(2)(a)