Article 16 Article 9 amended (changes to the monitoring methodology plan)
Article 9 is amended as follows.
After paragraph 2 insert—
“2a.Where the operator has any relevant product benchmark sub-installation, relevant heat benchmark sub-installation, relevant fuel benchmark sub-installation or any relevant process emissions sub-installation within the meaning of Article 4(9), the operator must modify the monitoring methodology plan to reflect the boundaries of the sub-installation that apply as a result of the requirement in Article 10(4a).”.
After paragraph 5 insert—
“5a.Paragraphs 3, 4 and 5 do not apply to a modification made to a monitoring methodology plan pursuant to paragraph 2a. Instead:
(a)the operator must notify the regulator of the modification of the monitoring methodology plan on or before 30th September 2026;
(b)the modification of the monitoring methodology plan is subject to approval by the regulator;
(c)once approved, the modification will take effect on 1st January 2027.”.
In paragraph 6(d)—
after “paragraph 3” insert “or 5a”;
after “paragraph 4” insert “or the date of the approval referred to in paragraph 5a(b)”.