# Growth and Infrastructure Act 2013, Paragraph 5


After paragraph 2 insert—
“The first review date: mineral planning authorities in England
2A (1) In the application of this Schedule in relation to a mineral planning authority for an area in England, “first review date” means the date set by the authority in accordance with sub-paragraph (2) below as the first review date for the purposes of the first periodic review of the mineral permissions relating to a mining site.
(2) That date may not be earlier than the relevant date found under paragraph 3 below in relation to the site.
(3) This paragraph is subject to paragraphs 3A and 5 below (power to specify different relevant date, and postponement of first review date).
The first review date: mineral planning authorities in Wales
2B (1) In the application of this Schedule in relation to a mineral planning authority for an area in Wales, “first review date” in relation to a mining site means the relevant date found under paragraph 3 below in relation to the site.
(2) This paragraph is subject to paragraphs 3A and 5 below (power to specify different relevant date, and postponement of first review date).”

---
Source: https://www.legislation.gov.uk/ukpga/2013/27/schedule/3/paragraph/5 (the official version)
Page: https://openlegislation.uk/growth-and-infrastructure-act-2013/schedule-3/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.