# The Harwich Parkeston Quay Harbour Revision Order 2010, Article 18: Arbitration

Extent: E+W+S

Where under any provision of this Order, including any provision applied by this Order, any difference is to be referred to or settled by arbitration, then such difference shall be referred to and settled by a single arbitrator to be agreed between the parties, or, failing agreement, to be appointed on the application of either party (after notice in writing to the other) by the President of the Institution of Civil Engineers.

---
Source: https://www.legislation.gov.uk/uksi/2010/626/article/18 (the official version)
Page: https://openlegislation.uk/harwich-parkeston-quay-harbour-revision-order-2010/article-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.