# The Health and Safety and Nuclear (Fees) Regulations 2022, Regulation 15C: Fees payable in relation to offshore wind or marine energy installations


(1) A fee is payable to the Executive by the client of an offshore wind or marine energy installation project for the performance by or on behalf of the Executive, or by an inspector appointed by it, of the functions specified in paragraph (2).
(2) The functions referred to in paragraph (1) are any functions conferred on the Executive or the inspector by the 1974 Act which relate to the enforcement of any of the relevant statutory provisions against one or both of the following—
(a) the client in relation to any work, including construction work, carried out for the offshore wind or marine energy installation project;
(b) a contractor in relation to any work, including construction work, carried out by that contractor on or in connection with that project.
(3) A fee is payable to the Executive by the operator of an offshore wind or marine energy installation for the performance by or on behalf of the Executive, or by an inspector appointed by it, of the functions specified in paragraph (4).
(4) The functions referred to in paragraph (3) are any functions conferred on the Executive or the inspector by the 1974 Act which relate to the enforcement of any of the relevant statutory provisions against one or both of the following—
(a) the operator in relation to any work relating to the operation of an offshore wind or marine energy installation;
(b) a contractor in relation to any work carried out by that contractor on or in connection with the operation of that installation.
(5) In this regulation—
“client”, “construction work” and “project” have the meanings given in regulation 2(1) of the Construction (Design and Management) Regulations 2015;
“energy structure” and “renewable energy zone” have the meanings given in article 9 of the Health and Safety at Work etc. Act 1974 (Application Outside Great Britain) Order 2013;
“offshore wind or marine energy installation” means—
(a)an installation of one or more energy structures and technology, including cables, within the territorial sea or a renewable energy zone for the purposes specified in article 9(1)(a) to (c) (the production of energy from water or wind) of the Health and Safety at Work etc. Act 1974 (Application Outside Great Britain) Order 2013, or
(b)any activities within the territorial sea or a renewable energy zone that are associated with the installation referred to in paragraph (a) and are connected with or preparatory to the purposes specified in article 9(1)(a) to (c) (the production of energy from water or wind) of the Health and Safety at Work etc. Act 1974 (Application Outside Great Britain) Order 2013;
“offshore wind or marine energy installation project” means a project to design, construct, install, maintain, decommission or demolish an offshore wind or marine energy installation;
“operator” means the person appointed by the owner of the offshore wind or marine energy installation to execute the management functions for operations to be carried out at that installation or, where no such person has been appointed, the owner of that installation;
“owner” means in relation to an offshore wind or marine energy installation the person who controls the operation of that installation.
“territorial sea” has the meaning given in article 2 of the Health and Safety at Work etc. Act 1974 (Application Outside Great Britain) Order 2013.

---
Source: https://www.legislation.gov.uk/uksi/2022/1378/regulation/15C (the official version)