Regulation 5 Variation of heat network zone by local authority: consultation

Original text. Later amendments are not shown.

(1)

For the purposes of section 50(3) of the Act the persons to be consulted are as specified in paragraph (2) and the manner of consultation is as specified in paragraph (3).

(2)

The persons specified are—

(a)

any person who holds a heat network zone permit under section 56 of the Act in respect of that heat network zone,

(b)

in the case of a heat network zone where any part of the boundary of the heat network zone as varied would adjoin any part of the boundary of a neighbouring local authority, that local authority, and

(c)

in the case of a heat network zone which as varied would be within the area of a National Park, the National Park authority.

(3)

The local authority must publish—

(a)

a map showing the proposed varied heat network zone on their website, and

(b)

a notice in a local newspaper circulating in the area and on the internet which states—

(i)

which heat network zone the local authority proposes to vary, and

(ii)

how and by what date (being a date no fewer than 28 days after the notice is published) representations can be made.