(1)
Document name
(2)
Applicant’s Document reference
(3)
Revision number
(4)
Date
book of reference
4.3
7.0
February 2024
environmental statement
6.1, 6.2, and 6.3
2.0
August 2023 (unless otherwise stated below)
6.1.17
6.2.5
6.2.7
6.2.13 - 6.2.14
6.2.16-6.2.20
6.3.1 - 6.3.3
6.3.6 - 6.3.10
6.3.12
6.3.14 - 6.3.18
1.0
February 2023
6.3.4.1
1.0
March 2023
ExA.6.3.7.13-D3.V2
1.0
November 2023
6.1.0 - 6.1.3
6.1.7 - 6.1.9
6.1.12 - 6.1.15
6.1.18
6.1.20
6.2.1 - 6.2.3
6.2.6 - 6.2.12
6.2.15
6.3.6
6.3.14
2.0
August 2023
6.1.10
6.1.16
6.1.19
6.2.3 - 6.2.4
6.2.10
2.0
November 2023
6.3.6.9
3.0
August 2023
6.1.5
6.2.2
6.2.6
3.0
November 2023
6.2.6
4.0
December 2023
6.1.4
5.0
January 2024
6.1.11
4.0
January 2024
6.1.6
3.0
February 2024
ES technical note – updated information on cumulative projects
ExA.ESTN-Cumulative-D5.V4
4.0
February 2024
Appendix 8.13 – biodiversity net gain assessment report
ExA.6.3.8.13-D4.V2
2.0
January 2024
ES transport and access technical note – sensitivity of cowbridge road, bicker drove, and vicarage drove
ExA.ESTATN.D3.V1
1.0
December 2023
ES technical note – additional ecology information
ExA.ESTNE.D3.V1
1.0
December 2023
equality impact assessment
ExA.EIA-D3.V1
1.0
December 2023
ES transport and access technical note – assessment of triton knoll access track, doubletwelves drove and bicker drove
ExA.ESTATN-Access-D5.V1
1.0
February 2024
flood risk assessment
6.3.9.1
2.0
March 2023
important hedgerows plan
2.9
3.0
January 2024
interface area plan
ExA.BFInterface.D5.V1
1.0
February 2024
land and crown land plan
2.1
5.0
January 2024
outline energy storage safety management plan
7.11
3.0
January 2024
outline construction environmental management plan
7.7
6.0
February 2024
outline construction traffic management plan
7.10
5.0
February 2024
outline decommissioning and restoration plan
7.9
4.0
February 2024
outline design principles
7.1
4.0
January 2024
outline landscape ecological management plan
7.8
6.0
February 2024
outline operational environmental management plan
ExA.oOEMP-D5.V3
3.0
February 2024
outline soil management plan
7.15
3.0
February 2024
outline supply chain, employment and skills plan
7.12
4.0
February 2024
outline written scheme of investigation – evaluation
7.13
2.0
November 2023
outline written scheme of investigation – mitigation
7.14
2.0
November 2023
rights of way plan
2.3
4.0
January 2024
streets and access plans
2.7
5.0
January 2024
works plans
2.2
6.0
February 2024

---
Source: https://www.legislation.gov.uk/uksi/2025/85/schedule/11 (the official version)
Page: https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.