# The Heckington Fen Solar Park Order 2025, Paragraph 1: Commencing an arbitration

Extent: E+W+S

(1) The arbitration is deemed to have commenced when a party (“the claimant”) serves a written notice of arbitration on the other party (“the respondent”).
(2) The primary objective of these Arbitration Rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within 4 months from the date the arbitrator is appointed pursuant to article 38 of the Order.

---