  "url": "https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-13/paragraph-102",
  "json_url": "https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-13/paragraph-102.json",
  "legislation": "uksi/2025/85",
  "legislation_title": "The Heckington Fen Solar Park Order 2025",
  "legislation_url": "https://openlegislation.uk/heckington-fen-solar-park-order-2025",
  "path": "schedule/13/paragraph/102",
  "kind": "paragraph",
  "number": "102",
  "heading": null,
  "text": "The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 37 (certification of plans and documents, etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in a format specified by Network Rail.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 13 para. 102 in force at 17.2.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/85/schedule/13/paragraph/102",
    "retrieved_at": "2026-10-28T21:21:15.551430+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}