# The Heckington Fen Solar Park Order 2025, Paragraph 118: Access

Extent: E+W+S

If in consequence of the agreement reached under paragraph 112(1) or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable Viking Link to maintain or use the apparatus no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2025/85/schedule/13/paragraph/118 (the official version)
Page: https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-13/paragraph-118
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.