# The Heckington Fen Solar Park Order 2025, Paragraph 119: Arbitration

Extent: E+W+S

Save for differences or disputes arising under paragraph 113, any difference or dispute arising between the undertaker and Viking Link under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Viking Link, be determined by arbitration in accordance with article 38 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2025/85/schedule/13/paragraph/119 (the official version)
Page: https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-13/paragraph-119
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.