# The Heckington Fen Solar Park Order 2025, Paragraph 124

Extent: E+W+S

The undertaker must consult with Beacon Fen in the formulation of the proposed method of working and timing of execution of the undertaker’s works within the Interface Area, not less than 60 days prior to such works commencing, and have regard to reasonable representations received from Beacon Fen made at least 30 days prior to such works commencing.

---