# The Heckington Fen Solar Park Order 2025, Paragraph 70: Arbitration

Extent: E+W+S

Save for differences or disputes arising under paragraphs 62(2), 62(4), 63(1) and 64 any difference or dispute arising between the undertaker and NGET under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and NGET, be determined by arbitration in accordance with article 38 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2025/85/schedule/13/paragraph/70 (the official version)