  "url": "https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-2/paragraph-15",
  "json_url": "https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-2/paragraph-15.json",
  "legislation": "uksi/2025/85",
  "legislation_title": "The Heckington Fen Solar Park Order 2025",
  "legislation_url": "https://openlegislation.uk/heckington-fen-solar-park-order-2025",
  "path": "schedule/2/paragraph/15",
  "kind": "paragraph",
  "number": "15",
  "heading": "Operational noise",
  "text": "(1) Work No. 1A, Work No. 2, and Work No. 4 must not begin operating until an operational noise assessment containing details of how the design of Work No. 1A, Work No. 2 and Work No. 4 ensures the operational noise rating levels set out in Table 12.8 of Chapter 12 of the environmental statement are to be complied with has been submitted to and approved by both relevant planning authorities.\n(2) The measures as described in the operational noise assessment must be implemented and maintained as approved throughout the operation of the authorised development.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 15 in force at 17.2.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/85/schedule/2/paragraph/15",
    "retrieved_at": "2026-10-28T21:21:15.551430+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}