# The Heckington Fen Solar Park Order 2025, Paragraph 15: Operational noise

Extent: E+W+S

(1) Work No. 1A, Work No. 2, and Work No. 4 must not begin operating until an operational noise assessment containing details of how the design of Work No. 1A, Work No. 2 and Work No. 4 ensures the operational noise rating levels set out in Table 12.8 of Chapter 12 of the environmental statement are to be complied with has been submitted to and approved by both relevant planning authorities.
(2) The measures as described in the operational noise assessment must be implemented and maintained as approved throughout the operation of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2025/85/schedule/2/paragraph/15 (the official version)
Page: https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-2/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.