# The Heckington Fen Solar Park Order 2025, Paragraph 20: Soil Management Plan

Extent: E+W+S

(1) No phase of the authorised development may commence until a soil management plan (which must be substantially in accordance with the relevant part of the outline soil management plan) for that phase has been submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of North Kesteven and the Borough of Boston, both relevant planning authorities.
(2) The construction of any phase of the authorised development must be carried out in accordance with the approved soil management plan for that phase.

---
Source: https://www.legislation.gov.uk/uksi/2025/85/schedule/2/paragraph/20 (the official version)
Page: https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-2/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

