# The Heckington Fen Solar Park Order 2025, Paragraph 6: Detailed design approval

Extent: E+W+S

(1) No phase of the authorised development may commence until details of—
(a) the layout;
(b) scale;
(c) proposed finished ground levels;
(d) external appearance;
(e) hard surfacing materials;
(f) vehicular and pedestrian access, parking and circulation areas, junction improvements and passing places;
(g) refuse or other storage units, signs and lighting;
(h) drainage, water, power and communications cables and pipelines; and
(i) programme for landscaping works,
relating to that phase have been submitted and approved in writing by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of North Kesteven and the Borough of Boston, both relevant planning authorities in consultation with the county authority.
(2) The details submitted must accord with the outline design principles and the flood risk assessment and, where relevant, demonstrate how they have taken account of relevant results of any archaeological investigations or archaeological evaluations carried out pursuant to requirement 12.
(3) The authorised development must be carried out in accordance with the approved details.
(4) Sub-paragraph (1) does not apply to the matters listed under sub-paragraph (1)(f) if consent has already been given to the details of those works pursuant to articles 9, 10, or 12.

---
Source: https://www.legislation.gov.uk/uksi/2025/85/schedule/2/paragraph/6 (the official version)
Page: https://openlegislation.uk/heckington-fen-solar-park-order-2025/schedule-2/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.