# The Helios Renewable Energy Project Order 2025, Paragraph 12: Public rights of way management plan


(1) No phase of the authorised development may commence and no decommissioning will be undertaken until a public rights of way management plan for any sections of public rights of way shown to be temporarily closed on the rights of way and access plans for that phase has been submitted to and approved by the local planning authority in consultation with the relevant highway authority.
(2) The plan must include details of—
(a) measures to minimise the length of any sections of public rights of way to be temporarily closed; and
(b) advance publicity and signage in respect of any sections of public rights of way to be temporarily closed.
(3) The public rights of way management plan must be implemented as approved unless otherwise agreed with the local planning authority, in consultation with the highway authority.

---
Source: https://www.legislation.gov.uk/uksi/2025/1372/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/helios-renewable-energy-project-order-2025/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.