# The Helios Renewable Energy Project Order 2025, Paragraph 18: Hydrogeological Risk Assessment


No phase of the authorised development which requires horizontal direct drilling or any other trenchless utility installation methods may commence until a hydrogeological risk assessment , the scope of which will be agreed in consultation with the Environment Agency, has been submitted to and approved by the local planning authority in consultation with the Environment Agency.

---