  "text": "In this Schedule—\n“access rights” means rights over land to—\n(a) alter, improve, form, maintain, retain, use (with or without vehicles, plant and machinery), remove, reinstate means of access to the authorised development including visibility splays and road widening and to remove impediments (including vegetation) to such access; and\n(b) pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development;\n“cable rights” means rights over land to—\n(a) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures and to connect such cables and services to the on-site substation;\n(b) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain watercourses, public sewers and drains and drainage apparatus and equipment;\n(c) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain landscaping and biodiversity measures;\n(d) remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development; and\n(e) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove vegetation and restrict the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development;\n“railway crossing rights” means rights over land to—\n(a) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures and to connect such cables and services to the NGET Drax 132kV Substation;\n(b) remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development; and\n(c) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development;\n“substation connection rights” means rights over land to—\n(a) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures and to connect such cables and services to the NGET Drax 132kV Substation;\n(b) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain watercourses, public sewers and drains and drainage apparatus and equipment;\n(c) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain landscaping and biodiversity measures;\n(d) remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development; and\n(e) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development;\n“vegetation maintenance rights” means rights over land to—\n(a) plant, inspect, alter, remove, replace, retain, renew, improve and maintain vegetation and restrict or prevent the removal of vegetation for the purposes of the authorised development and in connection with the authorised development.\n(1)\nPlot number(s)\n(2)\nWork No.\n(3)\nPurpose for which rights may be acquired\n1\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n2\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n3\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n4\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n5\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n6\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n7\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n8\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n9\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n10\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n11\nWork No. 1, 4, 7, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n12\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n13\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n14\nWork No. 1, 4, 7, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n15\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n16\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n17\nWork No. 4, 7, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n18\nWork No. 4 and 8\nAccess rights, cable rights\n19\nWork No. 4, 4A, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n20\nWork No. 4 and 4A\nAccess rights, cable rights\n21\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n22\nWork No. 4, 4A, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n23\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n24\nWork No. 1, 2, 3, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n25\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n26\nWork No. 1, 4, 4A, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n27\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n28\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n29\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n30\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n31\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n32\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n33\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n34\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n35\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n36\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n37\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n38\nWork No. 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n39\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n40\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n41\nWork No. 4 and 8\nAccess rights, cable rights\n42\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n43\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n44\nWork No. 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n45\nWork No. 1, 4, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n46\nWork No. 1, 4, 5, 8 and 9\nAccess rights, cable rights, vegetation maintenance rights\n47\nWork No. 1, 4 and 9\nAccess rights, cable rights, vegetation maintenance rights\n48\nWork No. 4 and 5\nAccess rights, cable rights\n49\nWork No. 4 and 5\nAccess rights, cable rights\n50\nWork No. 5\nAccess rights, cable rights\n51\nWork No. 5 and 8A\nSubstation connection works\n52\nWork No. 5 and 8A\nAccess rights, cable rights, railway crossing rights\n53\nWork No. 5 and 8A\nSubstation connection works, railway crossing rights\n54\nWork No. 5 and 8A\nSubstation connection works, railway crossing rights\n55\nWork No. 5 and 8A\nAccess rights, cable rights, railway crossing rights\n56\nWork No. 5 and 8A\nSubstation connection works, railway crossing rights\n57\nWork No. 5 and 8A\nSubstation connection works, railway crossing rights\n58\nWork No. 5, 6A and 8A\nSubstation connection works, railway crossing rights\n59\nWork No. 5 and 8A\nSubstation connection works, railway crossing rights\n60\nWork No. 5 and 8A\nSubstation connection works, railway crossing rights\n61\nWork No. 5\nAccess rights, cable rights\n62\nWork No. 5\nAccess rights, cable rights\n63\nWork No. 5\nAccess rights, cable rights\n64\nWork No. 5\nAccess rights, cable rights\n65\nWork No. 5\nSubstation connection works\n66\nWork No. 5, 6 and 6A\nSubstation connection works\n67\nWork No. 5\nSubstation connection works\n68\nWork No. 5, 6 and 6A\nSubstation connection works\n69\nWork No. 5 and 6\nSubstation connection works, railway crossing rights",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1372/schedule/7/paragraph/1",
    "retrieved_at": "2026-10-28T21:07:54.016827+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}