# The Helios Renewable Energy Project Order 2025, Paragraph 26


Any dispute arising between the undertaker and the drainage authority under this Part of this Schedule, if the parties agree, is to be determined by arbitration under article 39 (arbitration), but otherwise is to be determined by the Secretary of State for Energy Security and Net Zero on a reference to them by the undertaker or the drainage authority, after notice in writing by one to the other.

---
Source: https://www.legislation.gov.uk/uksi/2025/1372/schedule/9/paragraph/26 (the official version)
Page: https://openlegislation.uk/helios-renewable-energy-project-order-2025/schedule-9/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

