  "url": "https://openlegislation.uk/helios-renewable-energy-project-order-2025/schedule-9/paragraph-89",
  "json_url": "https://openlegislation.uk/helios-renewable-energy-project-order-2025/schedule-9/paragraph-89.json",
  "legislation": "uksi/2025/1372",
  "legislation_title": "The Helios Renewable Energy Project Order 2025",
  "legislation_url": "https://openlegislation.uk/helios-renewable-energy-project-order-2025",
  "path": "schedule/9/paragraph/89",
  "kind": "paragraph",
  "number": "89",
  "heading": null,
  "text": "The provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and Network Rail and, in the case of paragraph 103 of this Part of this Schedule any other person on whom rights or obligations are conferred by that paragraph.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1372/schedule/9/paragraph/89",
    "retrieved_at": "2026-10-28T21:07:54.016827+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}