# High Peak Mining Customs and Mineral Courts Act 1851, Order for a new Trial.


In the High Peak Small Barmote Court, held at the Day of
Between A.B., Plaintiff,
and
C.D., Defendant.
It is ordered, That the Judgment in this Case, and all subsequent Proceedings thereon, be set aside, and a new Trial had between the Parties [here state the Terms and Conditions, if any, of such new Trial].
Given under the Seal of the Court, this Day of in the Year 185 By the Court,
A.B., Steward.

---