# High Speed Rail (West Midlands - Crewe) Act 2021, Schedule 16: Temporary possession and use of land: table of land


(1)
(2)
(3)
(4)
(5)
Area
Number of land shown on deposited plans
Purpose for which temporary possession may be taken
Specified authorised works
Specified works which may be carried out
County of Staffordshire
District of Lichfield
Parish of Kings Bromley
3, 6, 8, 10a, 11a, 18a, 19, 32a, 34, 36a, 36b, 46, 57, 60, 69, 74, 78, 82, 83, 85, 89, 103, 107, 114, 123, 159, 164, 165, 168, 170, 173, 174, 180, 181, 183, 188, 199, 201, 208, 212, 216, 218, AP1-1
Diversion or installation of, or works to, utilities apparatus
Diversion or installation of, or works to, utilities apparatus
219, AP2-89a, AP2-89b
Provision of access for construction and diversion of, or works to, utilities apparatus
Diversion or installation of, or works to, utilities apparatus
221, 224, 226 to 228, 230 to 237, 239, 240, 247, 268 to 270, 272, AP2-104
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
Parish of Longdon
1, 2
Provision of access for construction and diversion of, or works to, utilities apparatus
Diversion or installation of, or works to, utilities apparatus
Parish of Armitage with Handsacre
1
Provision of environmental mitigation
Environmental mitigation works
Parish of Mavesyn Ridware
12, 77, 78
Creation of new public right of way
Creation of new public right of way
Works required in connection with the provision of a new public right of way
AP2-24, AP2-55, AP2-58, AP2-59
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
Parish of Colton
101, 102, 142, AP2-30, AP2-37, AP2-37b, AP2-61
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
189a, 194
Provision of access for construction and diversion of, or works to, utilities apparatus
Diversion or installation of, or works to, utilities apparatus
Borough of Stafford, Parish of Colwich
66, 84, 88, 89
Creation of new public right of way
Creation of new public right of way
Works required in connection with the provision of a new public right of way
87
Creation of new public right of way and provision of access for utility works
Creation of new public right of way and diversion or installation of, or works to, utilities apparatus
Works required in connection with the provision of a new public right of way
122, 139, 166, 181, AP2-7, AP2-64
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
AP2-69, AP2-70
Provision of access for construction works
Diversion or installation of, or works to, utilities apparatus
Borough of East Staffordshire
Parish of Abbots Bromley
AP2-32, AP2-100, AP2-101, AP2-104, AP2-106 to AP2-111, AP2-113, AP2-115, AP2-116, AP2-119
Provision of access for construction works
Diversion or installation of, or works to, utilities apparatus
Parish of Hoar Cross
AP2-10, AP2-12, AP2-14, AP2-16, AP2-17, AP2-19, AP2-21, AP2-24, AP2-27, AP2-30, AP2-33, AP2-35
Provision of access for construction works
Diversion or installation of, or works to, utilities apparatus
Parish of Newborough
AP2-7, AP2-9, AP2-10, AP2-12
Provision of access for construction works
Diversion or installation of, or works to, utilities apparatus
Borough of Stafford, Parish of Ingestre
AP2-1
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
Parish of Tixall
3a, 9, AP2-14
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
AP2-2
Provision of access for construction and diversion of, or works to, utilities apparatus
Diversion or installation of, or works to, utilities apparatus
Parish of Hopton and Coton
46, 59, 67, 69, 71, 86, 87, 90, 110, 113, 120, 125, 126, 129, 131 to 133, 135, 137, 139, 143, 146, 182, 185a, AP2-23, AP2-29, AP2-61, AP2-67, AP2-69, AP2-75
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
179
Provision of access for utility works and creation of new public right of way
Diversion or installation of, or works to, utilities apparatus and creation of new public right of way
Works required in connection with the provision of a new public right of way
Parish of Salt and Enson
1
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
Parish of Marston
10, 17, 21, 33, 72, 79, AP2-1 to AP2-7, AP2-15, AP2-33, AP2-35
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
Parish of Whitgreave
AP2-3, AP2-4
Creation of a new public right of way
Creation of a new public right of way
Works required in connection with the provision of a new public right of way
Parish of Stone Rural
36, 38, 58a, AP2-9, AP2-13, AP2-15, AP2-16, AP2-43
Creation of new public right of way
Creation of new public right of way
Works required in connection with the provision of a new public right of way
52, 67, 136, 138, AP2-20, AP2-21, AP2-34 to AP2-37, AP2-40, AP2-46, AP2-47
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
AP1-17, AP1-22
Diversion or installation of, or works to, utilities apparatus
Diversion or installation of, or works to, utilities apparatus
Parish of Swynnerton
66, 70, 74, 138, 147, 160, 164, 171, 173, 176, 178, 302 to 304, 317, 318, AP2-5 to AP2-7, AP2-12
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
91c, AP1-3, AP1-5, AP1-7, AP1-8, AP1-10, AP1-12 to AP1-15
Diversion or installation of, or works to, utilities apparatus
Diversion or installation of, or works to, utilities apparatus
AP2-57
Creation of a new public right of way
Creation of a new public right of way
Works required in connection with the provision of a new public right of way
Borough of Newcastle-under-Lyme
Parish of Whitmore
51, 55
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
102a, AP2-12
Creation of new public right of way
Creation of new public right of way
Works required in connection with the provision of a new public right of way
Town of Newcastle-under-Lyme
AP2-15, AP2-16
Worksite and access for construction
Works Nos. 78F ,78G and 78H
Parish of Madeley
7, 207
Provision of environmental mitigation
Environmental mitigation works
38, 181, 195, 196, 201
Creation of new public right of way
Creation of new public right of way
Works required in connection with the provision of a new public right of way
93, AP2-25, AP2-27, AP2-29, AP2-34
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
County of Cheshire
Borough of Cheshire East
Parish of Blakenhall
22, 26a, 33, 37, 42, 78, 107, 137, 139
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
Parish of Chorlton
2, 10, 11
Provision of access for utility works
Diversion or installation of, or works to, utilities apparatus
14, 53, 58, 60a
Creation of new public right of way
Creation of new public right of way
Works required in connection with the provision of a new public right of way
Parish of Basford
21
Creation of new public right of way
Creation of new public right of way
Works required in connection with the provision of a new public right of way

---
Source: https://www.legislation.gov.uk/ukpga/2021/2/schedule/16 (the official version)
Page: https://openlegislation.uk/high-speed-rail-west-midlands-crewe-act-2021/schedule-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.