No party structure notice under section 3 of the 1996 Act is required before the exercise of any right conferred by section 2 of that Act (right to repair etc party wall) for the purposes of or in connection with—
(a) the construction of the works authorised by this Act, or
(b) the maintenance of any such work during the period beginning with the date on which the work is completed and ending 5 years after the date on which it is brought into general use.

---