# The Highland Regional Council (Abhainn Mhungasdail) Water Order 1992, Article 5: Water rights


(1) During the construction of the works the Council may take from the said Abhainn Mhungasdail such water as they may require for such construction.
(2) After the completion of the works the Council shall not—
(a) take any water from the said Abhainn Mhungasdail so as to reduce the rate of flow therein below 386 cubic metres per day as measured through or over an approved gauge (part of Work No.1);
(b) in any one day take from the said Abhainn Mhungasdail a quantity of water greater than 50 cubic metres as measured through or over an approved gauge (part of Work No.2).

---
Source: https://www.legislation.gov.uk/uksi/1992/998/article/5 (the official version)
Page: https://openlegislation.uk/highland-regional-council-abhainn-mhungasdail-water-order-1992/article-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.