# Highways Act 1980, Section 105CC: Timing of conclusion and decision

Extent: E+W

The project authority must—
(a) reach the reasoned conclusion required by section 105CA(1)(b), and
(b) decide whether or not to proceed with the relevant construction or improvement,
within a reasonable period of time (having regard to the nature and complexity of the project) beginning on the day on which the authority begins the consideration required by section 105CA(1)(a).

---