# The Highways (SSSI Diversion Orders) (England) Regulations 2007, Regulation 8: Claims for compensation in respect of orders

Extent: E+W

(1) A claim made in accordance with section 28 of the Act (compensation for loss caused by public path creation order), as applied by section 121(2) of the Act, in consequence of the coming into operation of an order shall be made in writing and shall be served on the council, or, in the case of an order made by the Secretary of State, on the authority nominated by the Secretary of State as provided by section 28(3) of the Act (as it applies by virtue of section 121(2)(a) of the Act), by delivering it to the offices of the council or the authority (as the case may be), addressed to its Chief Executive, or by sending it by prepaid post so addressed.
(2) The time within which any such claim shall be served shall be six months from the date on which the order in respect of which the claim is made has come fully into force.

---
Source: https://www.legislation.gov.uk/uksi/2007/1494/regulation/8 (the official version)
Page: https://openlegislation.uk/highways-sssi-diversion-orders-england-regulations-2007/regulation-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.