Schedule 2 Approved plans to be inserted into Part 3 (Approved plans) of Schedule 1 (Authorised project) to the 2013 Order
Original text. Later amendments are not shown.
| Drawing number | Rev | Drawing Title | Scale | Paper size |
| Ancillary, Office and Storage |
|---|
| Off Site Delivery Checkpoint |
|---|
| HINK-A2-HUT-00-GP-020 | 01 | Roof Plan and Elevations | 1:100 | A1 |
| Drawing number | Rev | Drawing Title | Scale | Paper size |
| Emergency Response Centre |
|---|
| HINK-A2-HUM-00-GP-020 | 01 | Roof Plan | 1:100 | A1 |
| HINK-A2-HUM-00-GE-001 | 01 | Elevations | 1:100 | A1 |
| HINK-A2-HUM-00-GE-002 | 01 | Elevations | 1:100 | A1 |
| Drawing number | Rev | Drawing Title | Scale | Paper size |
| Emergency Response Energy Centre |
|---|
| HINK-A2-HDU-00-GP-020 | 01 | Roof Plan and Elevations | 1:100 | A1 |