Table 1 (corrections to the Articles)

Provision

Erroneous text

Correction

Article 2(1), definition of “undertaking”“mean”Substitute “means”
Article 8(3)“section 106A”Substitute “section 106(14)”
Article 12(2)“Sections 61(9)”Substitute “Section 61(9)”
Article 16“the footpath implementation plan”Substitute “a footpath implementation plan”
Article 25(4)The whole paragraphSubstitute “Subsection (2) of section 10 of the 1965 Act applies to paragraph (2) as it applies to section 152(3) of the 2008 Act by virtue of section 152(5) of that Act.”
Article 27(1)“the new rights”Substitute “the rights”
Article 38(2), definition of “restricted land”“sheet no. 3”Substitute “sheet no. 5”
Article 44(6)“A may serve or sending”Substitute “A may serve or send”
Article 49, definition of “general direction”“article 72”Substitute “article 71”
Article 52(6)(b)“First Schedule of”Substitute “First Schedule to”

Table 2 (corrections to Schedule 1)

Provision

Erroneous text / omission

Correction

Part 1, description of Work No. 1A, paragraph (c)“listed at 1(a)”Substitute “listed at (a)”
Part 1, description of Work No. 1A, paragraphs (d)(i) and (e)(i)“Safeguard; Buildings;”Substitute “Safeguard Buildings;”
“Fuel Building; Hall;”Substitute “Fuel Building Hall;”
Part 1, description of Work No. 1A, paragraph (o)“a sea walls”Substitute “a sea wall”
Part 3, list of plans for Conventional Island (Unit 2), Hydrazine and Ammonia StorageFor drawing number HINK-A2-SIR-02-GA-001, no scale is listed in the third column and no paper size in the fourth columnInsert “1:100” in the third column and “A1” in the fourth column
Part 3, list of plans for Remaining Balance of Plant and Other Plant (Shared Between both Units), Attenuation Pond“HINK-A2-01-HXO-00-GA-001”Substitute “HINK-A2-HXO-00-GA-001”
Part 3, list of plans for Junction 24The last two rows under the heading “Warehouse Building”Delete these rows
Part 3, list of plans for Highway improvements to A38 Bristol Road/The Drove JunctionThe scale of drawing number 900 is given as 1:1000For “1:1000” substitute “1:1500”
Part 3, list of plans for Highway improvements to A38 Bristol Road/Wylds Road JunctionThe paper size for drawings numbers 1000 and 1002 is given as A1For “A1” substitute “A2”

Table 3 (corrections to Schedule 2)

Provision

Erroneous text

Correction

Paragraph 1(1), definition of “permanent buildings or structures”“C3, J23-3, J24-2 and WP2”Substitute “C5, J23-4, J24-3 and WP3”
Paragraph 1(1), definition of “start-up and shut-down”“22 (start-up) means the periods of 30 minutes before the opening up of sites of those works and”Substitute “22 means the periods of 30 minutes before the opening up of sites of those works (start-up) and”
Paragraph 2, first sentence“PW1 to PW36”Substitute “PW1 to PW24”
Paragraph 3, requirement P15, paragraph (b)“PW31”Substitute “PW20”
Paragraph 4, requirement MS2, paragraph (1)“has been submitted”Substitute “have been submitted”
Paragraph 4, requirement MS2, paragraph (1)(e)“200 µg/m3”Substitute “200 µg/m3”
Paragraph 4, requirement MS7, paragraph (2)The whole paragraphSubstitute “Notwithstanding paragraph (1) any additional means of enclosure of that part of the site which is the subject of the Hinkley Point C Nuclear Site Licensing Licence Condition Arrangements – Assessment Report: ONR-CNRPAR-12-129 revision 0 (20th November 2012) shall only be installed after it is safe to erect and maintain an appropriate means of marking the boundary of that part.”
Paragraph 4, requirement MS8, paragraph (1)“Office of Nuclear Regulation”Substitute “Office for Nuclear Regulation”
Paragraph 4, requirement MS9, paragraph (1)“from the site”Substitute “from the HPC Development Site”
Paragraph 4, requirement MS9, paragraph (2)“West Somerset district Council”Substitute “West Somerset District Council”
Paragraph 4, requirement MS11, paragraph (1)(a) and (d)“MS10”Substitute “MS9”
Paragraph 4, requirement MS11, paragraph (2)“West Somerset district Council”Substitute “West Somerset District Council”
Paragraph 4, heading of requirement MS16“Building Design”Substitute “Interim Spent Fuel Store”
Paragraph 4, requirement MS26, paragraph (2)“have been be completed”Substitute “have been completed”
Paragraph 4, requirement MS28, paragraph (1)(h)“and the HPC Accommodation Campus (Work No. 3)”Delete these words
Paragraph 4, requirement MS36, paragraph (1)“and shall be kept for a minimum of two years from the date of the flight” in the second sentenceDelete these words
Paragraph 4, requirement MS38“the relevant planning authority”Substitute “West Somerset District Council”
Paragraph 5, requirement J2, paragraph (1)“the relevant planning authority”Substitute “West Somerset District Council”
Paragraph 6, requirement CW2, paragraph (1)(d)“Second Issues Specific Hearing”Substitute “Second Issue Specific Hearing”
Paragraph 10, requirement CB7, paragraph (1)“has been submitted”Substitute “have been submitted”
Paragraph 12, requirement C9, paragraph (1)“C4”Substitute “C5”
Paragraph 13, first sentence“refers to the Order limits”Substitute “refers to the land within the Order limits”
Paragraph 13, requirement J23-2, paragraph (1)“chapter 16”Substitute “chapter 14”
Paragraph 13, requirement J23-13, paragraph (2)“engineering detail”Substitute “engineering details”

Table 4 (corrections to Schedule 14)

Provision

Erroneous text

Correction

Paragraph 3, sub-paragraph (2)(c)“square metres of gross floorspace”Substitute “square metres of gross floor space”
Paragraph 4, sub-paragraph (2)(a)“the undertaker shall submit the appeal documentation to the Secretary of State”Substitute “the undertaker shall submit to the Secretary of State”
Paragraph 5, definition of “major detailed requirements”“J23-4, J24-3, and WP3”Substitute “J23-5, J24-4, and WP4”